Beneficiary: S.C. IMMOKIK S.R.L.
General Contractor: S.C. Retter Projectmanagement S.R.L.
Share: 100%
Contract Value: 396.999 EUR
Contract Period: 04/2017 – 12/2017
Complete refurbishment of an old store – Baumarket – in a Kika store. The works include the construction of a mezzanine level and the extension of the storage roof. The design, architectural, structural and HVAC design, as well as the authorization procedure, were carried out by RETTER Projectmanagement.
Micro Pills: 1.220 m
Mezzanine Level: 3.270 m2
New Concrete Floor: 2.220 m²
New Roof Area: 730 m²
Sales Sector Area: 9.300 m²
Storage Area: 2.800 m²